Pertamina Mandalika International Street Circuit

THE PROJECT

Dromo joined the Pertamina Mandalika International Circuit upgrade in July 2022 to investigate earlier surface failures and engineer a full-track response. The layout itself remained substantially unchanged, but the three-dimensional track design was revised to improve surface evenness, drainage and run-off performance. Dromo developed the racing asphalt in Europe, refined it with local materials on site and supported contractor PT PP through production and paving.

The track’s three-dimensional design was revised without changing its layout, to improve surface evenness and drainage and prevent standing water. The entire track required resurfacing, and the run-off areas at selected corners required enlargement. The promoter, MGPA, appointed general contractor PT PP (Persero) Tbk to carry out the works.

The original works were scheduled for completion by the end of September 2022. Technical difficulties with local aggregate production delayed paving until late October 2022, at the start of Lombok’s rainy season. Dromo developed the asphalt mix in its European laboratories and refined it on site.

An asphalt plant with a production capacity exceeding 240 tonnes per hour produced the bespoke racing mix, Rinjani. Named after Lombok’s volcano, the mix used locally sourced aggregates to improve the sustainability of the works. Production trials established the Job Mix Formula (JMF), followed by paving trials to confirm the mix and its suitability for placement.

Dromo and its partners supported PT PP (Persero) Tbk with equipment, raw materials and production-process requirements, helping the contractor implement the track design and meet the client’s requirements.

COUNTRY:

Indonesia

TEAM LEADER:

Jarno Zaffelli

PROJECT TEAM:

Sanjay Walia (Project Manager),
Federico Vennarucci (Head of design),
Filippo Piccoli (Site Manager),
Francesco Crotti (Pavement specialist),
Elisabetta Maria Terenziani,
Geronimo Aroldi,
Tatiana Rota.

CONTRACTOR:

PT PP (Persero) Tbk

WORK:

Investigate, engineer and resurface

MIX:

Rinjani

YEAR:

2022

Project engineering in detail

Diagnosing a complete pavement system

The work treated the track as more than a wearing course. Levels, water paths, aggregate production, mix behaviour and construction equipment were reviewed together. Because the works moved into Lombok’s rainy season, the relationship between surface geometry, drainage and production control was central to the delivery strategy.

Developing the Rinjani racing asphalt

The bespoke mix was named Rinjani after the Lombok volcano from which local aggregates were sourced. A plant capable of producing more than 240 tonnes per hour supported the programme. Laboratory design was followed by job-mix and paving trials so that the formulation could be adjusted to the available materials and verified before full production.

Technical support from plant to track

Dromo worked with project partners on equipment, raw materials and production procedures, then connected those controls to paving and the final track geometry. This end-to-end involvement reduced the gap between a laboratory specification and the surface actually delivered under tropical site conditions.

Related Dromo capabilities

Project evidence

Verified project register

Investigation, resurfacing and extension.

The completed 2022 assignment is recorded as a combined investigation, surface and masterplanning phase.

Investigation

Existing-track assessment

The documented scope begins with investigation of the operating circuit.

Surface

Circuit resurfacing

Resurfacing is explicitly identified in the project record.

Development

Extension and masterplan

The assignment also records an extension and masterplanning scope.


Project evidence / 01

Diagnose the complete pavement system.

The Mandalika response began with levels, water paths, surface condition and delivered geometry. Survey and diagnostic evidence separated the visible failure from its geometric, material and construction causes.

Read: resurfacing without losing the intended geometry

Dromo engineers reviewing track data on a monitor at Mandalika
Diagnosis began with measured evidence rather than a like-for-like replacement of the wearing course.
Dromo surveyor using a total station on the Mandalika circuit
Geometric surveying connected levels, crossfall and water paths to the resurfacing design.
Close-up of a Dromo surface measurement instrument on the Mandalika track
Local surface measurements supported the diagnosis and the definition of corrective work.

Project evidence / 02

Develop the Rinjani mix around real local materials.

European laboratory development was followed by local aggregate control, job-mix trials and paving trials before full production.

Aggregate production equipment used for the Mandalika racing asphalt
Local aggregate production became part of the engineering problem, not merely a supply input.
Laboratory test on an asphalt specimen developed for Mandalika
Laboratory evidence was used to quantify the response of the project-specific racing asphalt.
Technician carrying out material-control work for the Mandalika asphalt mix
The mix moved from European laboratory development to local refinement and verification.

Read: what makes racing asphalt different

Project evidence / 03

Connect milling, paving and compaction to the design.

The new surface was delivered as a controlled sequence across production, logistics, equipment, levels and field decisions.

Close-up of milling work removing the Mandalika racing surface
Controlled removal prepared the circuit for geometric correction and the new pavement system.
Aerial view of the coordinated paving train resurfacing the Mandalika main straight
Plant, haulage, paving and compaction were coordinated as one continuous delivery sequence.
Aerial view of paving equipment resurfacing a curve at Mandalika
Paving through the curve had to preserve the designed levels, transitions and drainage behaviour.
Resurfacing equipment and crews working at night at Mandalika
Night operations protected the compressed programme while maintaining production and delivery control.

Project evidence / 04

Verify the result under tropical operating conditions.

The completed asset links racing surface, drainage, run-off and venue operation within the Lombok climate.

Dromo engineers walking the Mandalika track between paving equipment
Engineering decisions continued at the work face, connecting specification to the surface being delivered.
Completed Mandalika corner with new racing surface, kerbs and run-off
The completed corner records the relationship between surface, kerbs, run-off and three-dimensional geometry.
Panoramic aerial of Mandalika circuit under a dramatic sunrise sky
Mandalika after delivery: a complete racing asset embedded in the Lombok landscape.